Price Electric’s team is working to upgrade the Des Moines Metro Wastewater Reclamation Authority at 3000 Vandalia Road, Des Moines. Our VCS department laid out all the PVC and fiberglass conduit to provide quality design. The team has prepared the duct bank and underground electrical and set in place two 2500KW Caterpillar natural gas generators in the power generation building. The project is designed to help with Flood Mitigation efforts in Des Moines and will be completed in 2023. The Des Moines Wastewater Reclamation Authority (WRA) is a state of the art, 50 MGD wastewater treatment facility. The WRA treats an average of 5708 million gallons of wastewater per day. It is the largest wastewater treatment facility in Iowa. Price Electric is an Electric Industrial Contractor.
Des Moines Metro Wastewater Reclamation Authority
Des Moines, IA
Completion: 2023