Venice Gardens Water Reclamation Facility

Venice, Florida

The Venice Gardens Water Reclamation Facility (WRF) Effluent Transfer Pump Station project took place in Venice, Florida.

Price Electric handled the demolition of three 225-amp outdoor disconnects and three indoor 75-horsepower variable frequency drives (VFD), along with all associated conduits and wiring.

Our team then installed new conduits and wiring to accommodate four 75HP VFDs and integrated four new 225-amp stainless steel disconnects with a smooth transition from above-ground to underground conduits.

Additionally, new control circuits were introduced for a comprehensive system integration.